The project, expected to take approximately six months, involves installing parallel crossings on every entry and exit to create a safer environment for all road users. To expedite the process with minimal disruption, teams will be working day and night. Daytime works will not involve traffic lights or road closures, but night works (8pm to 6am) will require temporary traffic lights and road closures to manage traffic flow during layout changes.
Initial works, including overnight temporary traffic lights, are already in progress. Overnight closures of individual roundabout arms are scheduled to begin in late November, with signed diversions in place. Works will pause for a few weeks over Christmas. Updates will be posted on the project webpage as plans may change due to weather dependency.
Recent achievements include the completion of kerbing around the new central island, the road foundation, and the renewal and adjustment of manhole covers to the new road surfacing levels. Topsoil has also been placed in the new roundabout area, with care taken to protect remaining trees.
Potential risks identified include a gas leak adjacent to the site in Parkway, which is being addressed with Southern Gas Networks, and potential delays due to ongoing works at National Highways' Dennis Roundabout. Planning for the next phase of Boxgrove works is ensuring diversion routes are not impacted, and evening events at Spectrum Leisure Centre will be accommodated.
Forthcoming works include laying tarmac layers, installing new signposts, and commencing works on Boxgrove Road from 30 November 2026, involving overnight road closures with an approved diversion route.
The investment aims to create safer, more people-friendly streets, encouraging walking and cycling. The project is funded by central government through Active Travel England with an expected cost of £2 million. Development followed extensive community engagement in 2023 and 2024, showing strong support.
Residents will be informed via letters, advance warning signs, and webpage updates. Disruption will be minimised for residents and businesses. Noise reduction measures will be taken during night-time working. Three smaller trees will be relocated, and remaining large trees on the roundabout will be kept, with some size reduction.